 |
Wanamaker Road, 37th to 41st Street –
Topeka, Kansas
Safety was the issue for both the City of Topeka and Shawnee
County when they joined together on planning for the
multi-phase Wanamaker Corridor project. This project is the
first in a series of improvements being made to transform
the roadway from an old two-lane county road to a
multi-lane, high volume urban arterial to serve increasing
demand as development continues on the southern edge of the
city. Included in the improvements are two multi-lane
roundabouts and a five-lane roadway connecting the
intersections.
Coordination was the key for Bartlett & West after being
awarded the project. Working with both municipal entities as
well as the Auburn-Washburn School District, Kansas
Department of Transportation, contractors and land owners
meant proactive communication and stringent planning was
required to meet the needs of this very visible project.
Bartlett
& West’s engineering services on this project resulted in a
national project of the year award by the American Public
Works Association.
|
|

 |
Kasold Drive, Bob Billings Parkway to Clinton Parkway –
Lawrence, Kansas
Improving traffic flow and safety on a key Lawrence artery
prompted the City to ask for an engineering study on a
one-mile stretch of Kasold Drive. The roadway, a four-lane
divided arterial carrying nearly 20,000 vehicles per day,
lacked turning lanes at intersections between Bob Billings
and Clinton Parkways and sight distance along much of the
route was substandard and few sidewalks existed throughout
the project area.
Bartlett
& West was selected to provide the preliminary study for
this corridor which included development of several
horizontal and vertical alignment alternatives in order to
provide protection of the existing landscape berm on the
east side of Kasold Drive; identification of potential
utility conflicts; comparison of pavement sections;
development of construction sequencing options; and
estimation of construction costs. A sidewalk addition
required construction of retaining walls ranging from two to
more then ten feet in height. Several public meetings and
City Commission presentations were conducted to obtain
feedback and provide responses.
After
the study was presented, construction decisions were made
and plans included details and profiles for streets, storm
sewers, and two new waterlines, retaining wall profiles,
paving and structural details, traffic signal modifications,
construction sequencing, pavement marking and signing plans,
as well as cross sections.
Reconstruction of this major north/south arterial has
significantly improved traffic flow throughout the corridor,
providing safety to thousands of motorists each day.
Recurring maintenance funds formerly dedicated to roadway
repairs can now be shifted to other projects and a new
pedestrian path on the roadway offers residents access that
was previously nonexistent.
|
 |
I-70, Wabaunsee & Shawnee Counties – Kansas
This portion of I-70 was the first segment to start being
paved and to be completed in the national interstate system
so
keeping
this historic portion of I-70 safe for drivers was the
motivation behind upgrading the infrastructure to meet new
safety standards.
The I-70
project involved design for the reconstruction of more than
eight miles of four-lane divided interstate roadway. The design
focused on upgrading geometric layouts of interchanges and
roadway grading to current standards. There were four
existing interchange access points within the project limits
and these interchanges were evaluated and redesigned to
incorporate current safety elements for proper design speeds
and adequate acceleration/deceleration lane lengths.
Design
and plan preparation services provided by Bartlett & West
included the necessity to carry traffic through construction
as well as access and traffic control during construction.
Right-of-way requirements included impact on many residences
and businesses. The Bartlett & West team provided plan and
specification preparation, construction sequences, hydraulic
and drainage design, bridge rehabilitation and replacement
design and estimate of construction cost.
In
addition to engineering design and plan preparation
services, Bartlett & West also provided photogrammetry and
surveying services including aerial targets, GPS horizontal
and vertical control, reestablishment and setting of base
line, setting and monument side road alignments, section
corner, bridge surveys, hard pavement shots at tie-ins,
location existing drainage structures and utility locations.
|

|
Strother Road – Lee’s Summit, Missouri
Fast-paced development calls for fast-paced infrastructure
improvements and that is what was needed for the Strother
Road Interchange project in Lee’s Summit. To provide
economic development opportunities to the Strother Road
corridor, this highly developing area is in need of a new
interchange on M-291/I-470.
The
construction of a diamond interchange on I-470 will not only
provide access to a future development area for economic
expansion, but the new interchange will also provide traffic
congestion relief for this busy stretch of interstate by
constructing a parallel city collector with additional
access and egress points other than I-470. In addition to
the interchange itself, auxiliary lanes with shoulders will
be constructed along the outside of the existing facility
from Woods Chapel Road to Colbern Road, helping to
facilitate traffic weaving patterns.
The Strother Road portion of the project under I-470 will
feature two through lanes each way with separate turning
lanes for access to or from I-470. Sidewalks will be built
along each side for pedestrian traffic and the bridge itself
will feature a decorative stone form linear on the outside
faces and a rock blanket spill slope for aesthetic
additions. New highway signs, ramp lighting, pavement
markings and traffic signals will complete the I-470
interchange project. |
 |
Fairchild Storm Sewer Separation – Topeka, Kansas
Creating a wetland park with native grasses, diverse plants
and a natural wildlife habitat was the result of some
environmentally friendly planning by Bartlett & West on the
Fairchild Storm Sewer Separation project. Instead of
replacing an outdated pump station and an egg-shaped brick
combined sewer, as called for in the North Topeka Stormwater
Master Plan, Bartlett & West’s proposal called for a
re-routing of the sewer which eliminated the need for a pump
station altogether and proved a more economical solution.
The
6,000-foot storm sewer project ultimately incorporated a
downstream area into a wetland park at the same time it
provided flood relief to 33 intersections in north Topeka
and will enable future separation projects to occur by
providing a downstream conveyance system for existing storm
sewer systems. Flood relief hasn’t been the only
environmental improvement as wastewater flow has been
removed from a drainage system that at one time directed
runoff into the Kansas River.
|
|
Return to Projects
page |
|