|
Need to
Know—Using Owner-Supplied Materials
By Jim
Lennington, PE
There are times when it may make sense for a facility owner
to pre-purchase materials for installation. In regional
water system development one of the more common examples of
this is the purchase of process equipment prior to final
design and construction. The primary reasons for this are to
allow the treatment process to be selected in advance based
on pilot testing of available equipment and to allow the
design of the facility to incorporate the dimensions, piping
connections and other features of the process equipment that
will be used verses developing a less refined design to
allow the incorporation of multiple supplier options. Another
reason for pre-purchasing equipment is the potential for
saving cost by avoiding the contractor's markup, which in
our experience is typically 10%-15% for materials purchased
from a vendor.
There are however, some considerations which should be
included in the decision making process before equipment is
pre-purchased.
Contract Administration
The potential for saving
money by avoiding the contractor's markup on equipment is
partially offset by increased contract administration.
Rather than having one contract with a contractor, the owner
and engineer have another set of contract documents to
develop and administer, including pay estimates, change
orders, and other written communication instruments. The
submittal process will still take place but may be
streamlined due to the lack of general contractor as a
middle man. The owner's legal counsel has two sets of
documents to review and approve, and so on. Costs for these
items may not be readily apparent, but if the equipment
purchase is not substantial, i.e. less than $100,000, these
administrative costs could easily exceed the cost savings.
Contract Documents
Contract documents form the
basis of the legal arrangement between an owner, engineer,
and a contractor and aid in assigning the risk on the
project. In the procurement contract the arrangement is
between buyer (owner), and seller, with many of the same
provisions as in the standard construction contract. The
engineer acts as the owner’s representative as in a
construction contract. A key difference is that instead of
“substantial completion,” the main milestone is the date of
delivery, or acceptance date, for the equipment being
purchased. The owner and engineer need to understand the equipment delivery dates will have an effect on the
final construction schedule, and that proper coordination is
required. The owner needs to consider and understand the
risk that delayed equipment delivery will delay construction
and potentially lead to contractor claims for damages. The
opposite also needs to be considered: that the equipment is
ready for delivery but can't be accepted because of a delay
in progress of the construction contract. It is reasonable
in such an event for the equipment supplier to claim
additional costs due to delayed delivery. The Engineers
Joint Contract Documents Committee (EJCDC) Standard General
Conditions for Procurement Contracts expressly states
(7.03.D) the seller is entitled to additional costs
arising of out a delay attributable to the buyer. These costs
could include financing charges, storage costs, increased
shipping, delayed profits, or other such reasonable costs
incurred by the equipment supplier.
Insurance and Liability during Construction
Typically, the procurement
contract has provisions for how and when the equipment is to
be delivered. The contract typically specifies at what point
the owner takes possession of the equipment and that the
owner is responsible for unloading, storage, and
installation. The owner and engineer in turn need to
incorporate the appropriate provisions in the contract for
installation of the equipment in order to avoid a situation
in which the owner is responsible for the equipment while it
is being installed by the installation contractor. In most
instances the installation contractor is made responsible
for coordinating and taking delivery of the equipment,
storing it according to the supplier's instructions, and its
proper installation. It is a good idea to require that the
contractor have prior experience with installation of
equipment of a similar nature. Also, the provisions of the
installation contract need to be clear on the insurance
coverage required and who is responsible for the equipment
at various phases so that any damage to the equipment is
covered. The Builder's Risk policy for the installation
contract should be in an amount that includes the
owner-purchased equipment. Removal of the exclusion on the
Contractor's General Liability policy for "property under
the care, custody, and control" of the contractor can be
difficult to get from the contractor's insurer.
Sales Taxes, Use Tax, and Contractor’s Excise Tax
Most states require payment
of sales taxes for purchase of equipment, supplies, and
services by utilities and governmental entities, or a use
tax when the materials are provided by an entity which is
not responsible for the payment or collection of sales tax.
When a contractor purchases and installs equipment for
regional or community water systems, the contractor is
considered the final user or consumer of those materials.
These sales are subject to sales taxes. When a contractor
installs equipment purchased by someone else the contractor
has to pay a use or sales tax on the equipment or certify
that the taxes have already been paid by the owner. This
requirement should not be forgotten and should be included
in one or the other of the contracts. The final
certification that the sales taxes have been paid can be
included as required documentation of contract close-out.
Some states
also have a contractor’s excise tax, or a tax on
construction of facilities, that is paid by the contractor
and incorporated into his price. That tax is on the total
amount of construction and would include any materials
supplied by the owner. As such, the contractor must be
advised of the costs so that the appropriate tax can be
incorporated into their bid.
Summary
Owner-supplied materials can have their advantages in the
construction of projects, but those advantages also come
with some items to be carefully considered prior to
proceeding. Proper care in planning and coordination is
required to minimize any unintended circumstances that could
lead to claims or unforeseen costs due to improper
assignment of responsibilities. |