|
Rural and regional water systems are organic. They are a
living entity, changing and
growing with varying degrees of frequency. Demand may
outpace supply. Systems are expanded. Infrastructure is
replaced. New water sources are added. Though sometimes
overlooked in the drive to make system improvements,
construction permit applications
are required in most states from a variety of regulatory
agencies.
Lack of proper permitting can stop a project in its tracks.
Every improvement, whether costing $100,000 or $100,000,000,
requires a permit. And it takes time. Knowing the
who, what, when, where and how can really pay off by
avoiding unnecessary delays to construction. Even so, plan
on 60 to 90 days for a typical construction permit.
Permits are needed before constructing virtually any
improvements to the system,
including water lines, storage facilities, treatment plants
or water supply wells.
Typically, a state agency charged with protecting the
environment will issue the
construction permit. The particular agency, or what it is
called, varies by state. In some states, it may be a
Department of Natural Resources, for example. In another
state it
might be a Department of Health and Environment. Either way,
the agency will need to review the preliminary engineering
report, plans and specifications to confirm that the
project complies with minimum requirements.
These documents must be submitted and then reviewed by the
agency’s staff engineers. Systems need to build the typical
two-to-three month review time into their project
schedule. This can be a problem for smaller projects where
there might be pressure to
move the project forward.
Depending on the circumstances of the improvement, other
permits might be required.
For example, a U.S. Army Corps of Engineers permit is needed
if the project falls under
its jurisdictions marked on a U.S. Geological Survey
topographic map. The review process might take 30 to 60
days, and the permit will be good for a specific period of
time, often
two years from the date of determination. The owner may also
be required to certify that
the disturbed stream bed and banks have been put back to
their original condition. Army Corps of Engineers permitting can be avoided if no open
cut construction occurs;
so many systems consider directional boring to cross the
streams in question, saving
the time of a Corps review.
Permits may
be required to cross state and county roads. Agencies
involved may or may not allow open cutting, even on gravel
roads. Even if directional boring is used to go under the
road, encasement of the line will probably be required or
warranted.
If federal
funds are used for the project, further permitting will be
required. A number of agencies may be involved. One system
project with USDA Rural Development funding required reviews
by Department of Interior Fish and Wildlife Service, State
Office of Administration, DNR Division of Geology and Land
Survey, DNR State Historic
Preservation Officer, Corps of Engineers, DNR Division of
State Parks, and State Department of Conservation. These
reviews may result in construction being restricted
to certain times of the year or techniques.
So sweat the details. Being aware of permitting requirements
will avoid potentially costly project delays. |